A Finance Ministry appeals ruling forces the Royal Thai Navy to rerun its 17 billion baht frigate tender; Hanwha Ocean can bid again and has gone to the ombudsman.

T
TaiwanDefence

Taipei ·

3 min read
Grey Royal Thai Navy stealth frigate sailing in formation on calm sea
File photo: Royal Thai Navy frigate HTMS Bhumibol Adulyadej (FFG 471) sails in the Gulf of Thailand during the CARAT Thailand exercise with the US Navy in June 2019. The image is not related to the new tender.US Navy photo by MC1 Toni Burton via Wikimedia Commons (public domain) Public domain (work of the US federal government)Mass Communication Specialist 1st Class Toni Burton, US Navyhttps://commons.wikimedia.org/wiki/File:HTMS_Bhumibol_Adulyadej_(FFG_471)_sails_with_naval_ships_from_the_U.S._and_Thailand_during_CARAT_Thailand_2019.jpg

TAIPEI —

The Royal Thai Navy said on 18 November that it will cancel the procurement of a new high-performance frigate awarded to South Korea's Hanwha Ocean and start the tender again, after a government appeals body found that the bidding terms broke procurement rules.

Navy spokesman Rear Admiral Chanin Sriyaphai said the move follows a ruling by the Appeals and Complaints Review Committee of the Comptroller General's Department at the Finance Ministry, issued under Section 119 of the 2017 public procurement act, which ordered the process scrapped and run again.

The committee had upheld a complaint from the Thai Frigate Building Consortium, The Star reported, citing Thai media.

A missing threshold

The dispute centres on the experience requirement. Finance Ministry rules require a tender to set a minimum value for a bidder's past contracts, at no more than half of the project budget, or about 8.5 billion baht for this 17 billion baht programme. The navy's terms of reference asked only for proof of an earlier frigate construction contract and set no value.

The spokesman acknowledged that the terms were incomplete and not in line with the law, and said the navy would respect the ruling. He argued that no high-performance frigate anywhere costs as little as 8.5 billion baht, which is why the figure had been left out, and denied any corruption or tailoring of the specification to suit one bidder.

Hanwha can bid again

Hanwha Ocean offered 16.73 billion baht on 8 September and was chosen as the winning bidder that month, but no contract was ever signed. The spokesman said the navy did not expect to be sued, because the process had reached only the announcement of a winner and the company had not invested or spent money on the project.

The ruling does not disqualify any company, so Hanwha Ocean and other qualified shipbuilders can take part in the new round, the navy said.

Financial News reported that Hanwha Ocean has filed a petition with Thailand's ombudsman asking it to examine whether the cancellation was lawful. A Hanwha official told Businesskorea the company had learned of the decision through media reports, was checking the official notice and would review its response.

The project covers building and delivering one 4,000-ton-class frigate and providing maintenance and support afterwards, according to Financial News, which added that HD Hyundai Heavy Industries, unsuccessful in the first round, has not decided whether to bid again.

Racing a 2027 deadline

The cancellation dissolves every committee tied to the project, including those for project management, the draft terms of reference, the procurement itself and the offset policy. The navy must now appoint new committees and write new terms before it can invite bids again.

The spokesman admitted that the dispute had already cost the navy time. Under its budget framework, the purchase must be completed within the 2027 fiscal year, by September 2027, so the new process has to start quickly. The navy commander, Admiral Nares Wongtrakul, has ordered it to be run strictly, transparently and fast.

According to The Star, Admiral Nares said the frigate is still needed to protect Thai sovereignty and maritime interests. Two Turkish shipbuilders, ASFAT and TAIS Shipyards, were among the six original bidders, and the review comes a month after Turkey signed a military cooperation agreement with Cambodia, with which Thailand has a border dispute.