Hanwha Aerospace starts building a 10 trillion won AI data centre for South Korea's military

The 180-megawatt centre in Changwon is due to open in part in July 2028, with the military keeping control of its data while Hanwha runs the servers.

T
TaiwanDefence

Taipei ·

2 min read
A line of six camouflaged tracked self-propelled howitzers fire their long barrels at once on a muddy range, with smoke trails rising against green hills
File photo: South Korean K9 Thunder self-propelled howitzers, made by Hanwha Aerospace, fire during a joint South Korea-US artillery exercise on 10 May 2016.Photo: US Army / Pfc. Dasol Choi (public domain), via Wikimedia Commons Public domain (US federal government work)Pfc. Dasol Choi, US Armyhttps://commons.wikimedia.org/wiki/File:Coordinated_thunder_-_1_of_7.jpg

TAIPEI —

Hanwha Aerospace is building a data centre dedicated to military artificial intelligence in Changwon, South Gyeongsang province, and has set aside 10 trillion won (about US$7.5 billion) for the first phase, the company said on 24 November. Part of the facility is due to start operating in July 2028, and the finished centre is planned to house high-density graphics processing unit (GPU) servers with a combined capacity of 180 megawatts.

The company presented the plan at the construction site on 24 November to Ha Jung-woo, vice chair of South Korea's National AI Strategy Committee, and to officials from the committee and the Defense Acquisition Program Administration (DAPA), the state arms procurement agency. The visitors were there to work out policies for bringing AI into the defence industry, according to Korean business media.

Military-owned data, contractor-run servers

Hanwha Group is considering an arrangement under which the military would own and control its data while a defence company runs the centre under contract. Because defence AI handles military information, the company said, the centre has to be isolated from outside networks, unlike commercial data centres, and needs high-level security and systems that keep it running during emergencies.

Hanwha estimates that it would take the Ministry of National Defense six to eight years to build its own AI data centre once feasibility studies, site selection, permits, design and construction are counted. The company argues that using a facility built in advance by the private sector could bring the military's adoption of AI forward by four to five years.

Scale and funding

The centre is being built on a site of about 43,000 square metres near Hanwha Aerospace's Changwon plant. Its planned 180-megawatt capacity equals roughly 13 percent of the output of a typical nuclear reactor, Chosun Biz and The Elec reported.

The project is part of a 55 trillion won investment plan announced in July by Hanwha Group senior vice chairman Kim Dong-kwan, which covers aerospace and defence AI projects in South Korea's southeast, including the Changwon complex. The group plans to expand its data centre business at home and abroad by linking the centres to its power generation assets.

An export angle

Hanwha also said it would consider offering AI data centres as part of export packages to countries that have adopted South Korean weapons systems, and described the Changwon centre as national core infrastructure that would help it expand into exports of integrated AI-based weapons systems.

The group already manages data for its defence affiliates at an integrated data centre in Jukjeon, Yongin, which it has run since 2011, and plans to draw on its experience designing and integrating systems for an AI data centre in the US state of Georgia, Chosun Biz reported.